Victorian Planning Permit

How the Process Works

Victoria — Planning & Environment Act 1987

Planning Permit Process

Step-by-step guide to obtaining a planning permit in Victoria.

1

Pre-Application Research

1–2 weeks
  • Check zone and overlays (SPEAR, council, SiteLogic)
  • Identify referral authorities (Parks Vic, Heritage Vic, etc.)
  • Optional: pre-application meeting with council planner
2

Prepare Application

2–4 weeks
  • Architectural drawings (plans, elevations, sections)
  • Arborist report (if trees affected)
  • Shadow diagrams, overlooking analysis if required
  • Application fee (varies by council, ~$800–$3,000)
3

Lodge with Council

Day 1
  • Online via SPEAR (Spatial Planning Electronic Application Resource)
  • Council checks application for completeness
  • May request further information (stops the clock)
4

Referral Authorities

2–4 weeks if triggered
  • Heritage Victoria, Melbourne Water, VicRoads, etc.
  • Each referral authority has 28 days to respond
5

Public Notice / Advertising

14–28 days (if required)
  • Notice on site + letters to adjoining owners
  • Objections can be lodged during notice period
  • If no objections: proceed to decision
  • If objections: council may hold mediation
Decision
Point

Approved

Notice of Decision (NOD): objectors have 28 days from its date to apply to VCAT. The permit issues if none do.

Refused

Applicant can appeal to VCAT within 60 days of refusal.

VCAT Appeal

+3–9 months. Mediation first; full hearing if no resolution.

Permit Issued

  • 2-year expiry to commence development (typical)
  • 4 years to complete development
  • Permit conditions must be read and understood before work begins

Timeframes are indicative only and vary by council, application complexity, and referral requirements. Consult your town planner for project-specific advice.